Deck timeline
A deck build runs in a fixed sequence: design and bids, permit application, utility locate through 811, footings, posts and beams, ledger and flashing, joists, framing inspection, decking, railing and stairs, then final inspection. The build itself is rarely the slow part - permit review and inspector scheduling are, and both are controlled by your local building department.
Before anything moves, the permit has to be applied for and the utility locate called in. Footings must not be built over septic systems, leach fields, utility lines or enclosed meters, so the 811 call is both a legal step and a design input. Ask your building department at the same time how long review takes and how much notice inspectors need.
Footings first, and they're weather-dependent. They must bear on undisturbed soil at least 12 inches below the undisturbed ground surface or below the frost line, whichever is deeper, and bearing conditions must be verified in the field by the building official before concrete is placed. Frozen or saturated ground stops this step regardless of anyone's schedule.
The framing inspection is the gate. It happens before the decking covers everything up. If your builder wants to lay boards before that inspection, stop them - that's the difference between a correction and a demolition.
Final inspection ends the project, not the last board. The deck should not be used or occupied until final inspection and approval is obtained. Plan your first cookout after that, not before.
Choosing decks timeline
The judgement calls that decide the bill, before anyone quotes you.
- Start the permit before you finalize materials Review time is the most common cause of delay and it's entirely outside your builder's control.
- Call 811 early It's free, it's required before digging, and it can change where footings go.
- Don't let decking go down before the framing inspection Covering unapproved framing is how a small correction becomes a teardown.
- Expect weather to move footing day Footings must bear on undisturbed soil below frost depth and be verified in the field before concrete.
- Tie the final payment to final approval The deck isn't finished until it's approved for use.
All decks timeline
Nothing published here yet. Tell us what you need and we'll match you with a pro who can answer it properly.
Where these figures come from
Sources last checked
- American Wood Council - DCA 6 Prescriptive Residential Wood Deck Construction Guide · retrieved 2026-07-26
- Fixr - Cost to Build a Deck · retrieved 2026-07-26
You know more than the last homeowner they quoted.
That is worth something only while you are still choosing. Tell us what is going on and we will match you with a few decks pros whose licence and insurance we have already checked - free, no obligation.
Free · No pressure · Only your matched pros get your details