A deck build runs in a fixed sequence: design and bids, permit application, utility locate through 811, footings, posts and beams, ledger and flashing, joists, framing inspection, decking, railing and stairs, then final inspection. The build itself is rarely the slow part — permit review and inspector scheduling are, and both are controlled by your local building department.

Before anything moves, the permit has to be applied for and the utility locate called in. Footings must not be built over septic systems, leach fields, utility lines or enclosed meters, so the 811 call is both a legal step and a design input. Ask your building department at the same time how long review takes and how much notice inspectors need.

Footings first, and they're weather-dependent. They must bear on undisturbed soil at least 12 inches below the undisturbed ground surface or below the frost line, whichever is deeper, and bearing conditions must be verified in the field by the building official before concrete is placed. Frozen or saturated ground stops this step regardless of anyone's schedule.

The framing inspection is the gate. It happens before the decking covers everything up. If your builder wants to lay boards before that inspection, stop them — that's the difference between a correction and a demolition.

Final inspection ends the project, not the last board. The deck should not be used or occupied until final inspection and approval is obtained. Plan your first cookout after that, not before.

How to choose

Start the permit before you finalize materials
Review time is the most common cause of delay and it's entirely outside your builder's control.
Call 811 early
It's free, it's required before digging, and it can change where footings go.
Don't let decking go down before the framing inspection
Covering unapproved framing is how a small correction becomes a teardown.
Expect weather to move footing day
Footings must bear on undisturbed soil below frost depth and be verified in the field before concrete.
Tie the final payment to final approval
The deck isn't finished until it's approved for use.
0 pages

All decks timeline

Nothing published here yet. Tell us what you need and we'll match you with a pro who can answer it properly.

FAQ

Decks timeline — common questions

Still have a question? Talk to our team →

The construction is usually the short part; permit review and inspection scheduling drive the calendar and both are set by your local building department. Ask them for current review times before you plan around a date.
Typically a footing or framing inspection before the structure is covered, and a final inspection. Your jurisdiction sets the exact schedule — confirm it when you apply.
No. Under the standard prescriptive deck guide, decks should not be used or occupied until final inspection and approval is obtained.
Permit review, inspector availability, weather affecting footings, and change orders. The first two are outside your builder's control; the third is partly, and the fourth is entirely on how well the scope was defined up front.
Sources

Where these figures come from

You know more than the last homeowner they quoted.

That is worth something only while you are still choosing. Tell us what is going on and we will match you with a few decks pros whose licence and insurance we have already checked — free, no obligation.

Get matched free

Free · No pressure · We never sell your details

(866) 582-8523 Get my free quote